PRIORITY DEVELOPMENT PROJECTS
(FUNDED BY THE 20% DEVELOPMENT FUND OF THE LGU)
BUDGET YEAR : 2024
SOCIAL SERVICES
HEALTH SUPPORT SERVICES
1. PURCHASE OF LOT FOR CONSTRUCTION OF MUNICIPAL SUPER HEALTH CENTER
Schedule of Release : 1st Quarter
Estimated Amount : 4,000,000.00
NUTRITION PROGRAM
1. Dietary Supplementation for Pre-School Children
Schedule of Release : 2nd quarter
Estimated Amount : 1,000,000.00
Estimated Amount : 1,000,000.00
ECONOMIC SERVICES
1. Construction of Barangay Access Roads (Canhaayon -Mahilum)
Schedule of Release : 2nd quarter
Estimated Amount : 1,500,000.00
Second Schedule of Release: 3rd Quarter
Estimated Amount : 3,800,000.00
Estimated Amount : 1,500,000.00
Second Schedule of Release: 3rd Quarter
Estimated Amount : 3,800,000.00
2. Rehabilitation and Concreting of Municipal Streets
Schedule of Release : 2nd Quarter
Estimated Amount : 2,500,000.00
Estimated Amount : 2,500,000.00
3. Concreting of Anolon to Dumpsite
Brgy. Road
Schedule of Release: 3rd Quarter
Estimated Amount : 1,000,000.00
Second Schedule of Release : 4th Quarter
Estimated Amount : 1,000,000.00
Estimated Amount : 1,000,000.00
Second Schedule of Release : 4th Quarter
Estimated Amount : 1,000,000.00
4. Construction of Municipal Drainage & Sewerage System (Poblacion 2)
Schedule of Release: 1st Quarter
Estimated Amount: 720,326.20
Estimated Amount: 720,326.20
5. Reclamation Development (Poblacion 1)
Schedule of Release : 4th Quarter
Estimated Amount: 5,000,000.00
Estimated Amount: 5,000,000.00
AGRICULTURAL SERVICES
1. Corn Production
Schedule of Release : 1st Quarter
Estimated Amount : 50,000.00
Estimated Amount : 50,000.00
2. Poultry and Livestock Production Program
Schedule of Release: 1st Quarter
Estimated Amount: 100,000.00
Estimated Amount: 100,000.00
3. Coffee Production
Schedule of Release: 1st Quarter
Estimated Amount : 50,000.00
Estimated Amount : 50,000.00
REHABILITATION OF RHU MAIN BUILDING AND BIRTHING CENTER
PROJECT COST : PHP 3,388,442.91
FUND SOURCES: HEALTH SERVICES CO 2020-20% DF
LOCATION: BRGY. POBLACION 2 , HINDANG , LEYTE
IMPLEMENTING AGENCIES: LGU HINDANG
CONTRACTOR: BERDS CONSTRUCTION
DURATION: 192 CALENDAR DAYS
STARTED: DECEMBER 16 , 2023
TARGET OF COMPLETION: JUNE 24, 2024